PCTO
Release plan
20/01/2020 – 19/05/2020
Revision History
Author | Date | Description |
---|---|---|
Enrico Bragastini | 20/01/20 | Initial Release |
Iteration #1
Object: The purpose of this iteration is to understand system requirements
Features / Activities / Deliverables | Estimated Effort | Actual Effort |
---|---|---|
Interview with the teacher | 1h | 2h |
Analysis of the data | 1h | 3h |
System use cases in summary form | 4h | 10h |
Totals | 10h | 25h |
Iteration #2
Object: The purpose of this iteration is to begin working on the project
Features / Activities / Deliverables | Estimated Effort | Actual Effort |
---|---|---|
ETL Process | 4h | 3h |
Database programming | 1h | 1h |
Front-end | 10h | 20h |
Back-end | 15h | 25h |
Totals | 30h | 49h |