PCTO

Release plan

20/01/2020 – 19/05/2020

Revision History

Author Date Description
Enrico Bragastini 20/01/20 Initial Release

Iteration #1

Object: The purpose of this iteration is to understand system requirements

Features / Activities / Deliverables Estimated Effort Actual Effort
Interview with the teacher 1h 2h
Analysis of the data 1h 3h
System use cases in summary form 4h 10h
Totals 10h 25h

Iteration #2

Object: The purpose of this iteration is to begin working on the project

Features / Activities / Deliverables Estimated Effort Actual Effort
ETL Process 4h 3h
Database programming 1h 1h
Front-end 10h 20h
Back-end 15h 25h
Totals 30h 49h